About

Projects

Learn about Projects for DC Water Investor Relations, including Anacostia River Tunnel Project, Small Diameter Water Main Replacement Project - Bloomingdale, and Filterate Treatment Facilities.

Anacostia River Tunnel Project

The Anacostia River Tunnel Project is the second in a series of four tunnels that will mitigate combined sewer overflows that are currently discharged to the Anacostia River. The 23 foot diameter tunnel is approximately 12,500 feet in length and extends from Robert F. Kennedy (RFK) Stadium in northeast DC to Poplar Point in southeast DC. In addition to the tunnel construction, DC Water has also been building surface facilities to divert the combined sewer overflows to the tunnel at various sites along the I-295 corridor, M Street SE and the Southeast Freeway. These facilities include deep shafts that range from 20 to 60 feet wide and large concrete structures to divert raw sewage from being discharged to the Anacostia River. The construction of these facilities is unparalleled in the District. Not since the construction of the original sewer system in the early 1900’s and the Metro has the District seen construction of this magnitude.

The Anacostia River Tunnel will connect with the Blue Plains Tunnel at Poplar Point and deliver captured combined sewer overflows to the Blue Plains Advanced Wastewater Treatment plant for treatment prior to discharge to the Potomac River. With the Blue Plains and Anacostia River Tunnels in service, DC Water will have met a key Consent Decree milestone in the Clean Rivers Project. In March 2018, it is anticipated that upon completion of this first phase of the Clean Rivers Project, combined sewer overflows to the Anacostia River will be reduced by 81 percent.

Small Diameter Water Main Replacement Project - Bloomingdale

DC Water will replace the existing 8 and 12-inch cast iron water mains in the Bloomingdale area as part of its Capital Improvement Program. These efforts will improve water quality and system reliability, increase water pressure, and maintain adequate flows.

Filterate Treatment Facilities

For decades, DC Water has been a pacesetter in restoring the Potomac River and Chesapeake Bay by improving the performance and treatment capabilities of the Blue Plains Advanced Wastewater Treatment Plant. The facility has successfully achieved nitrogen removal since 1999, and has exceeded the Chesapeake Bay Agreement goal of removing 40 percent of the total nitrogen (TN) in the effluent from the plant.

As part of a continuing effort to improve water quality, DC Water is designing facilities to reduce nitrogen discharges even further – to the limit of conventional treatment technology. These facilities, known as the enhanced nitrogen removal facilities (ENRF), are being constructed as part of our $3.8-billion, ten-year Capital Improvement Program (CIP).

The Filtrate Treatment Facilities (FTF) are part of this effort. This novel anammox-based side stream treatment process, called DEMON®, will be the largest of its kind in the world when the facility is commissioned. The DEMON® process represents a major breakthrough in nitrogen removal because it does not require the addition of methanol, uses 60 percent less energy than mainstream treatment and has the lowest greenhouse gas emissions of all the processes considered for this project. It could save DC Water more than $8 million a year in methanol and energy costs.

Long-term benefits include:
■    Lowest demonstrated energy demand of any biological treatment process.
■    No methanol or other supplemental carbon requirement.
■    Lowest greenhouse gas emissions.

The construction cost of this project is approximately $64 million.  Notice-to-Proceed was given to the contractor in March 2014, and the facility is expected to be online in 2017.

Update **

Project is currently 94% complete and scheduled to finish sometime in Q2 of 2018.

HQO

Currently, DC Water's administrative offices are spread across the District of Columbia in multiple facilities, including leased space. The Central Operations Facility at the Blue Plains Advanced Wastewater Treatment Plant serves as the Authority's de facto headquarters, which was not its original intended purpose. Meantime, process improvements at Blue Plains have consumed almost all 150 acres of the plant. By relocating nonessential personnel off of the Blue Plains industrial campus, DC Water will preserve what little remaining space exists - an irreplaceable commodity - for future process improvements if required by permit or desired for innovation.

The new headquarters will be built over an operating pump station in the Capital Riverfront neighborhood. With 151,300 gross square feet, it will house approximately 350 employees and will allow DC Water to consolidate its administrative offices in a single location. Construction began in 2016 and is expected to be completed in early 2018.

Rock Creek Green Infrastructure Project A

Rock Creek Project A is the first GI project to be constructed in the Rock Creek Sewershed to reduce the level of pollution to Rock Creek produced by the discharge of stormwater runoff and sanitary sewer flows, known as combined sewer overflows (CSOs).

Rock Creek Project A involves the construction of innovative GI technologies that include bioretention on planter strips and curb extensions, permeable pavement on streets and alleys and downspout disconnection (including rain barrels). These practices will manage stormwater by taking advantage of the earth's natural processes, such as allowing the water to infiltrate into the soil, evaporate into the air or be used by plants which expire it as vapor. In addition to managing stormwater, GI will contribute to beautifying the streetscape and making it safer and more welcoming for pedestrians, bicyclists and drivers.

Saint Elizabeth Water Tower

Through the Elevated Water Storage Tower Project, DC Water will perform water system improvements for the proposed Anacostia 2nd high service area. The proposed new service area and water storage tower will serve the southern section of the existing Anacostia 1sthigh service area, improving water quality, system reliability, water pressure and ensuring adequate flows throughout the system.

The project area for the water storage tower is located near the Saint Elizabeths Hospital National Historic Landmark (NHL). The proposed site for the new tank is adjacent to the newly constructed hospital facility. The new tower will permit demolition of the existing tower  which was originally build in the 1930s and is today semi operational and unable to provide adequate water pressure to the hospital facility.